This Fence Builder Left Me in the Dust: 320 Feet of Vinyl Fence in One Day

Aug 19, 2023 • 10 min read

Roughly 320 feet of vinyl fence. About 65 posts. Fifty-four sections and a gate. One four-person crew, digging holes, wet-setting concrete, and installing the fence in a single day.

That is a monster job. And Victor Vasquez’s crew wasn’t getting those numbers by pouring dry concrete mix into holes and moving on. They mixed their concrete in wheelbarrows, carried it to the posts, and still made impressive time.

I spent the day on this Salt Lake City job to find out where that speed came from. The plan was to stay out of the production work so I wouldn’t skew the results. Standing around while everyone else works is harder than it sounds, but it gave me a chance to notice the little things.

The biggest difference wasnstrong’t one fancy tool or one secret technique. It was a crew that kept eliminating unnecessary work.

Key Takeaways

  • Plan section spacing around rail lengths to reduce repetitive cutting, handling, and waste.
  • Keep concrete mixing and delivery supplied so post setting does not wait on each batch.
  • Use a consistent string-line method to make alignment easier to teach and verify.
  • Separate material problems from installation work whenever possible to keep the crew productive.

A Big Fence Job With Real Obstacles

It would be easy to explain away a fast installation by saying everything went perfectly. This one didn’t.

Along one side of the property, the new vinyl fence had to go right beside an existing chain-link fence. That meant keeping the auger clear of the neighbor’s fence while drilling close enough to put the new posts where they belonged.

Another stretch ran through a narrow gap between concrete surfaces. There was barely enough room for a vinyl post, much less a comfortable opening for digging tools. My first thought was that those holes would all need to be hand dug.

Narrow soil gap between two concrete surfaces beside old fence materials
This narrow opening was one of the biggest obstacles to keeping the digging moving.

Then there was the sprinkler pipe. Pulling an old post brought up a piece of irrigation line that had been embedded in its concrete footing. Later, another piece of buried irrigation tubing turned up along the fence line.

Victor’s response was practical: make sure the customer knows what happened. He also explained that his contract addresses concealed irrigation damage. That is worth noting as part of how he handles the business side, not as a promise that any particular contract clause resolves every situation.

The old fence was already out when I first looked over the project. Later in the day, we established that the crew had started removal around 8:15 a.m. Hole digging was underway around 9:00.

So this wasn’t simply a day of dropping panels into posts somebody else had prepared.

The Crew Starts Working Before There Is Time to Stand Around

The first thing I noticed was how quickly everyone got to work. When these guys got off the truck, they weren’t standing in a circle trying to figure out what was happening.

They started doing the work.

That sounds obvious, but on a four-person crew, small delays multiply. If everybody waits while one person makes each decision, production stops in several places at once.

Victor’s crew kept different parts of the job moving together: digging, staging posts, bringing materials forward, and preparing concrete. By just after 11:00 a.m., all the holes were dug, the posts were standing in the holes, the end posts were set, and the string line was up.

That early progress gave them the rest of the day to set posts, finish alignment, and assemble the fence.

Victor’s personal story makes the company he has built even more impressive. He talked openly about originally entering the United States without legal status, later becoming legally authorized, and now helping workers come legally to work with him. He jokes that his first fence job was cutting one to get here. Whatever the joke, he has built a serious fence business.

Lay Out the Fence to Avoid Repetitive Cutting

Victor does not like cutting rails. By the end of the day, that point was pretty clear.

His goal during layout was to make the sections work with the rail lengths so the crew could install them without trimming every piece. He was working through the spacing and a three-way connection early, before those decisions turned into extra work during assembly.

Good layout does more than make a fence fit the property. It determines how much handling and cutting the crew will have to do later.

Every unnecessary cut means another measurement, another trip to the saw, another offcut, and another opportunity to get something wrong. Repeat that across dozens of sections and it adds up.

There was some good-natured complaining about whoever had sold the job and created the layout challenge. Unfortunately for Victor, the salesperson was Victor.

Open the Concrete Just Enough to Get the Auger In

The narrow concrete gap turned out not to require the amount of hand digging I expected.

The crew used a large angle grinder with a masonry blade to make cuts in the concrete, then a jackhammer to remove the obstructing pieces. They opened enough space to lower a six-inch auger into position and clean out the hole afterward.

Round drilled hole beside cut concrete edges and broken concrete pieces
Removing a small amount of concrete gave the auger enough room to work.

That combination impressed me. Instead of fighting the restricted opening with hand tools for the entire hole, they dealt with the obstruction first and then used the equipment they already had.

I estimated at the time that a dedicated concrete saw might cost around $1,200, depending on the model, compared with perhaps $200 for the grinder. Those were rough comparisons, not current quotes, but the appeal was obvious: a relatively compact tool helped unlock a much faster digging method.

Concrete cutting also deserves proper dust control and protection. OSHA’s construction silica guidance is a useful reference when planning that work. The production lesson is to bring the right tools, not to skip the precautions that go with them.

Keep the Wet-Set Concrete Operation Supplied

Victor’s concrete setup was straightforward: two wheelbarrows of concrete in the rotation, with five-gallon water buckets kept full.

The point was to avoid running the operation one small batch at a time. The crew setting posts needed concrete available, and the people mixing needed water ready instead of stopping to fetch it.

Their mix was loose. You could move a shovel through it easily, and it flowed readily around the posts.

Loose wet concrete and a shovel inside a wheelbarrow

I saw two practical reasons for that consistency:

  • It took less effort to mix because the shovel moved through it easily.
  • It flowed around the post rather than requiring as much effort to place.

Now, before anybody gets excited, this was not a measured-slump demonstration or an engineered mix design. I acknowledged on site that this would not produce the strongest concrete the bagged material could potentially make.

My opinion was that it would serve this residential fence application, and I questioned whether it was any worse than the dry-packing methods often used to chase high production numbers. But that was a field judgment, not a strength test or proof that the two methods are equivalent.

Do not confuse an observed production method with a concrete specification. An engineered commercial project is a different situation, and required mix designs and installation instructions still matter.

A Block on a Bucket Makes Pouring More Controlled

One of my favorite details was almost laughably simple: a small wood block screwed to the bottom of a concrete bucket.

That block gave the worker a bottom handhold while tipping the bucket. Instead of wrestling a smooth bucket base, he could control the pour with both hands.

Gloved hand gripping a wood block attached to the bottom of a tilted bucket
A small bottom handle makes the bucket easier to control while pouring around a post.

The crew used the buckets to deliver concrete into the holes faster than shoveling it in, while keeping enough control to avoid pushing the bottoms of the posts out of position.

It is such a small modification that it is easy to overlook. But those are exactly the details worth noticing. A cheap improvement repeated all day can be more useful than an expensive tool that only comes out once.

Set the Bottoms First, Then Finish the Line and Height

Victor didn’t spend the initial setting stage making every post top perfect. He concentrated on getting the bottoms where he wanted them, then came back to finish the height and alignment while adjustments were still possible.

His string-line setup used little binder clips, the clips he carried on his hat. They held the string at the top of the end posts.

Small binder clip holding a yellow string at the top edge of a white vinyl post

With the reference established, he could work down the run and see which posts needed to come down, come up, or move slightly inward or outward.

He also checked the relationship between the fence and the ground. In one spot, the chosen top line meant removing a little dirt beneath the fence rather than throwing the whole run out of line to clear one high area.

The sequence was deliberate:

  1. Establish the post-bottom positions using the lower layout reference.
  2. Evaluate the overall top line and ground clearance.
  3. Adjust the post heights.
  4. Bring the post sides into alignment with the upper string.

Instead of treating each post as an isolated project, he treated the run as one continuous line.

String Line or Eyeball? We Had to Settle That One

Victor likes his string. I like sighting down a fence.

Naturally, that turned into a challenge.

My method is to look along both sides of the posts and bring their faces into alignment until the posts farther down the run seem to disappear behind one another. It is much like looking down a rifle sight.

When I set posts that way, I aim to have the inward and outward alignment handled during placement. Then I can concentrate on bringing the tops into the right line.

It works, but it takes practice. Lots of practice.

Height changes are part of that judgment, too. At one corner, carrying the line straight through would have left the fence higher than we wanted. Rather than create a sharp peak at one post, I spread the adjustment across about three sections so the top rolled through the change gradually.

Victor’s response was fair: he would use the string to establish the line and then use his eye to refine it. We were not as far apart as the argument made it sound.

The clear advantage of the string-line method is training. A newer installer can check a visible reference much more easily than reproduce someone else’s practiced eye. I still believe an experienced installer can be very fast by sight, but we teach new people with a string because it is much easier to learn and verify.

The Wrong Rail Lengths Didn’t Stop the Installation

For a man who had laid out the job to avoid cutting rails, getting a load of rails that were too long was a pretty good plot twist.

A substantial number needed cutting to fit the intended sections. Victor chose to exchange them for shorter rails instead.

Josh and I took the material back. I gave Victor plenty of grief about burning fuel just because he couldn’t stand cutting rails, but the important part was what happened at the jobsite: his crew kept working.

While we were gone, they continued preparing and assembling the fence. By the time we returned, the job was practically done.

That doesn’t prove exchanging material is always better than cutting it. Travel time, available labor, and the amount of cutting all matter. Here, the supply problem was handled separately enough that it didn’t bring the installation to a halt.

Build the Height Transitions Without Creating Rail Interference

The front of the job included a sloped transition from a taller privacy fence to a shorter section.

We build plenty of those in Florida. Sometimes they accommodate front-yard height restrictions, where a fence extending beyond the front of a building may need to drop from six feet to something closer to three-and-a-half or four feet. The actual limit depends on the local rules.

We also use transitions in backyards, such as stepping a six-foot vinyl fence down to four feet before meeting an aluminum fence.

Victor’s crew cut and assembled the transition quickly. One detail that matters is easy to miss: angle-cut the rail ends so they can fit together inside the shared post.

View into an open vinyl post showing rail ends meeting inside
The rail ends need clearance inside the post where the sloped and horizontal sections meet.

Leaving the interfering portions on those ends would make the rails run into one another inside the post. The finished outside appearance depends on getting that hidden connection right.

Use the Last Picket Offcut to Start the Next Section

Another small habit supported Victor’s effort to reduce waste.

When the last picket in a section needed to be ripped narrower, he didn’t automatically throw away the remaining strip. He used that piece to start the next section.

Other installers might save assorted strips and hope to find a use for them later, or alternate pickets in an attempt to use them up. Victor’s approach was immediate: finish this section, then carry the usable remainder into the next one.

The result blended into the fence, and less material went into the scrap pile.

That fits the same thinking behind his rail layout. Avoid unnecessary cuts where possible, and make useful cuts count when they are necessary. It is about profitability as much as speed.

The Result Was Fast, but the Ground Deserves Some Credit

At 2:29 p.m., the fence was far enough along that I expected the crew to be wrapped up, loaded, and heading down the road around 3:30.

The final count we discussed was 54 sections with a gate, roughly 320 feet of fence, and somewhere around 63 to 65 posts. The early estimates varied a little, but there was no question this was a substantial one-day installation.

We also agreed on an important limitation: the ground was good. Very good.

A boulder-filled job would have been a completely different story. Victor wasn’t pretending he could repeat this exact pace regardless of what was underground.

The physical effort was real, too. Near the end of the day, his hand cramped up. A productive system reduces wasted effort, but it doesn’t make fence building effortless.

What About Bracing the Posts?

One thing the crew didn’t do was install pairs of temporary 2-by-4 braces on every post while the concrete cured.

I am pretty outspoken about treating that as an automatic step on this kind of installation. Victor’s crew worked without that extra setup and removal, keeping the posts aligned through their setting process.

The useful takeaway is specific: bracing every post was not part of this crew’s method on this job. That is not a reason to disregard a fence manufacturer’s instructions or a project requirement.

Fast Fence Building Is a Collection of Small Decisions

Victor’s crew worked hard, but hard work alone doesn’t explain the day.

They started with purpose, laid out the fence to reduce cutting, opened obstructions so equipment could work, kept concrete supplies ready, and used simple tools to make repeated tasks easier. They had a consistent alignment method, kept installing through a material problem, and found a use for pieces that could have become waste.

Nothing about the job was completely trouble-free. That is what made it worth learning from.

The speed came from solving problems without letting every problem stop the crew. Put enough of those small decisions together, and a monster fence job starts looking like a day’s work.